Question: Activity Normal Time Manpower requirement 0-1 2 4 1-2 3 3 1-3 4 3 2-4 2 5 3-5 4 3 3-6 3 4 4-7 6

Activity Normal Time Manpower requirement
0-1 2 4
1-2 3 3
1-3 4 3
2-4 2 5
3-5 4 3
3-6 3 4
4-7 6 3
5-7 6 6
6-8 5 2
7-9 4 2
8-9 4 9

Using the above table information ,

  1. Re-arrange the activities suitably in order to reduce the existing total manpower.
  2. If only 9 workers are available for the execution of the project, then re-arrange the activities suitably for leveling the manpower resource.