Question: Activity Normal Time Manpower requirement 0-1 2 4 1-2 3 3 1-3 4 3 2-4 2 5 3-5 4 3 3-6 3 4 4-7 6
Activity Normal Time Manpower requirement 0-1 2 4 1-2 3 3 1-3 4 3 2-4 2 5 3-5 4 3 3-6 3 4 4-7 6 3 5-7 6 6 6-8 5 2 7-9 4 2 8-9 4 9
Using the above table information ,
- Re-arrange the activities suitably in order to reduce the existing total manpower.
- If only 9 workers are available for the execution of the project, then re-arrange the activities suitably for leveling the manpower resource.