Question: Activity Normal Time Predecessor Normal Cost Crash time A 6 - 1 0 0 3 B 8 - 2 0 0 8 C 1 0
Activity
Normal
Time
Predecessor
Normal
Cost
Crash
time
A
B
C A
D B
E B
F E
G CD
H F G
points
Under "normal" conditions what is the
earliest the project can be completed?
points
What is the critical path?
points
Suppose you wanted to complete the
project one week earlier than under normal
conditions. What activityies would you
choose to speed up
points
What would be the cost of the project if it
were reduced by one week?
BDGH
BEFH
ACGH
ACGHF
B
H
G
A
points
Under "crash" conditions, what is the
earliest the project can be completed?
point
Quality planning should be done:
point
Which of the following presents information in order of priority to assist focusing on the most
critical ones?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock