Question: Activity Normal Time Predecessor Normal Cost Crash time A 6 - 1 0 0 3 B 8 - 2 0 0 8 C 1 0

Activity
Normal
Time
Predecessor
Normal
Cost
Crash
time
A 6-1003
B 8-2008
C 10 A 2002
D 10 B 10005
E 9 B 5004
F 8 E 15006
G 9 C,D 8005
H 6 F, G 10004
3 points
Under "normal" conditions what is the
earliest the project can be completed?
3 points
What is the critical path?
3 points
Suppose you wanted to complete the
project one week earlier than under normal
conditions. What activity(ies) would you
choose to speed up.
3 points
What would be the cost of the project if it
were reduced by one week?
33
25
27
31
BDGH
BEFH
ACGH
ACGHF
B
H
G
A
3000
6300
14,500
5350
3
4
5
6
3 points
Under "crash" conditions, what is the
earliest the project can be completed?
1 point
Quality planning should be done:
1 point
Which of the following presents information in order of priority to assist focusing on the most
critical ones?
20
31
18
22

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!