Question: For the following Project: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Immediate Predecessor A 4 3 $2,000 $2,100 - B 2
For the following Project:
| Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost | Immediate Predecessor |
| A | 4 | 3 | $2,000 | $2,100 | - |
| B | 2 | 1 | $2,200 | $2,800 | - |
| C | 3 | 3 | $500 | $500 | - |
| D | 8 | 6 | $2,300 | $2,600 | A |
| E | 6 | 3 | $900 | $1,200 | B |
| F | 3 | 2 | $3,000 | $4,200 | C |
| G | 4 | 2 | $1,400 | $2,000 | E, F |
What is the total cost to complete the project in normal time?
| $4700 | ||
| $12300 | ||
| $14600 | ||
| $15400 |
Please highlight the answer