Question: Activity number Activity name Duration in hours Predecessor 1 Date/Location 1 - 2 Hotel booking 25 1 3 Arrival 15 1 4 On-site offers 20
Activity number Activity name Duration in hours Predecessor 1 Date/Location 1 - 2 Hotel booking 25 1 3 Arrival 15 1 4 On-site offers 20 1 5 On-site program 10 4 6 Send info to participants 1 2,3,4 7 Approval 30 5,6 8 Event start 5 7
Draw a network diagram (AOA)