Question: Activity on Edge For the graph in Figure 2, please calculate the earliest and latest time for all activities and events and write them down
Activity on Edge
For the graph in Figure 2, please calculate the earliest and latest time for all activities and events and write them down in a table. Also, please mark critical activities and answer what is the shortest possible duration of the whole project. Once again, please use edge weights to denote edges (activities).
Also, write down at least 2 possible topological orders of the partial order defined by the network. 