Question: Activity - on - Node refers to Microsoft Project's convention for developing networks. means that slack is present in an activity. means that slack is
ActivityonNode
refers to Microsoft Project's convention for developing networks.
means that slack is present in an activity.
means that slack is present on the critical path.
requires dummy nodes.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock