Question: Activity Optimistic Most Likely Pessimisitic Immediate Predecessor ( s ) START 0 0 0 long dash A 7 1 0 1 3 START B 0
Activity
Optimistic
Most Likely
Pessimisitic
Immediate Predecessors
START
long dash
A
START
B
A
C
A
D
B
E
D
F
C
G
D
H
G
I
C G
J
I
K
H
L
J K
FINISH
E F L
popup content ends Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.
LOADING... Click the icon to view the table.
Part
a Based on the critical path, find the probability of completing the office renovation project by days. Refer to the standard normal tableLOADING.... Make sure to round all intermediate calculations for te and variance to two decimal places.
The probability is
enter your response here. Enter your response rounded to four decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock