Question: Activity Optimistic Most Probable Pessimistic A 5 6 7 B 4 8 15 C 3 4 8 D 2 2 2 E 1 5 9

Activity Optimistic Most Probable Pessimistic
A 5 6 7
B 4 8 15
C 3 4 8
D 2 2 2
E 1 5 9
F 2 5 8
G 2 6 17
H 3 7 8
I 1 8 9

  1. What are the critical activities? If necessary, round your answers to two decimal places. If your answer is zero, enter 0.
    Activity Expected Time Variance
    A
    B
    C
    D
    E
    F
    G
    H
    I
    Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity
    A No
    B Yes
    C Yes
    D No
    E No
    F Yes
    G No
    H Yes
    I Yes
    Critical Path:
  2. What is the expected time to complete the project? If necessary, round your answer to two decimal places. E(T) = days
  3. Based only on critical path, what is the estimated probability that the project can be completed in 25 or fewer days? Variance = . If necessary, round your answers to two decimal places. Using the normal distribution, z = . If necessary, round your answers to two decimal places. If negative answer is required, enter the minus sign before the number. Probability of 25 days or less is . If necessary, round your answers to four decimal places. Note: Use Appendix B to identify the probability.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!