Question: Activity Optimistic Most (To) Probable Pessimistic Expected time(Te = (Tp) (To+4*Tm+Tp)/6) Early Late Finish Finish Slack Critical Path (Tm) 2 3 4 3.0 3 3

Activity Optimistic Most (To) ProbableActivity Optimistic Most (To) Probable

Activity Optimistic Most (To) Probable Pessimistic Expected time(Te = (Tp) (To+4*Tm+Tp)/6) Early Late Finish Finish Slack Critical Path (Tm) 2 3 4 3.0 3 3 0 Yes B 1 2 3 2.0 5 8 3 4 5 12 6.0 9 9 Yes D 3 3 11 5.0 00 ON 1 E 1 3 3 5 3.0 8 11 3 3 F 1 3 2.0 11 11 Yes G 1 8 9 7.0 15 16 1 | H 2. 4 6 4.0 15 15 0 Yes 2 4 12 5.0 20 20 0 Yes J 3 5 5 4.0 19 20 K 5 7 8 6.8 27 27 0 Yes Standard Deviation Expected Completion Critical Path