Question: Activity P on a project has exactly 5 predecessors A , B , C , D , and E whose early finish days are 2

Activity P on a project has exactly 5 predecessors A, B, C, D, and E whose early finish days are 22,32,38,50, and 32, respectively. (Here "day" means "days after project start".) What is the early start day of P?