Question: Question 26 (3 points) Saved Activity P on a project has exactly 4 predecessors A, B, C, and D whose early finish days are 20,
Question 26 (3 points)
Saved
Activity P on a project has exactly 4 predecessors A, B, C, and D whose early finish days are 20, 12, 38, and 32. (Here "day" means days after project start.) What is the early start day of P?
Question 26 options:
| 13 | |
| 38 | |
| 39 | |
| 21 |