Question: Activity Preceding Activity Estimated Duration A - 16 B A 7 C - 15 D B,C 15 E A 12 F E 15 G D,E

Activity Preceding Activity Estimated Duration
A - 16
B A 7
C - 15
D B,C 15
E A 12
F E 15
G D,E 17
H F 10
I G 14
J G,H 3
K J,I 13

Using AON notation, carryout both a forward and backward pass. What is the estimated total duration for the project? Identify all paths through the network. Which is the critical path? Which activities have slack time? Identify all burst activities and merge activities. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the projects schedule? Has the duration changed? Is there a new critical path? Show your conclusions.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!