Question: Activity Preceding Activity Normal Completion Time (week) Crashed Completion time (week) Crashed Cost per week A - 5 4 500 B A 7 7 700
| Activity | Preceding Activity | Normal Completion Time (week) | Crashed Completion time (week) | Crashed Cost per week |
| A | - | 5 | 4 | 500 |
| B | A | 7 | 7 | 700 |
| C | A | 6 | 4 | 600 |
| D | B,C,E | 9 | 8 | 800 |
| E | B | 6 | 4 | 400 |
| F | D,E | 10 | 8 | 500 |
| G | D | 9 | 8 | 900 |
i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. Mark: 2 ii. Find the completion time of the project and the critical path. Mark: 3 iii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Mark: 4 iv. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. Mark: 4 v. Highlight the critical and non-critical activities of the finally completed project by taking into account the crashed times of activities. Mark: 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts