Question: Activity Preceding Activity Normal Completion Time (week) Crashed Completion time (week) Crashed Cost per week A - 5 4 500 B A 7 7 700

Activity

Preceding

Activity

Normal Completion

Time (week)

Crashed Completion

time (week)

Crashed Cost per

week

A

-

5

4

500

B

A

7

7

700

C

A

6

4

600

D

B,C,E

9

8

800

E

B

6

4

400

F

D,E

10

8

500

G

D

9

8

900

i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. Mark: 2 ii. Find the completion time of the project and the critical path. Mark: 3 iii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Mark: 4 iv. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. Mark: 4 v. Highlight the critical and non-critical activities of the finally completed project by taking into account the crashed times of activities. Mark: 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!