Question: Activity Preceding Activity Normal Completion Time (week) Crashed Completion time (week) Crashed Cost per week A - 5 4 $500 B A 6 5 $400

Activity

Preceding

Activity

Normal Completion

Time (week)

Crashed Completion

time (week)

Crashed Cost per

week

A

-

5

4

$500

B

A

6

5

$400

C

-

10

8

$500

D

B, C

9

8

$700

E

D

5

4

$600

F

E

7

6

$500

G

D

10

9

$800

  1. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. Mark: 4
  2. Highlight the critical and non-critical activities of the finally completed project by taking into account the crashed times of activities. Mark: 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!