Question: Activity Preceding Activity Normal Completion Time (week) Crashed Completion time (week) Crashed Cost per week A - 5 4 $500 B A 6 5 $400
| Activity | Preceding Activity | Normal Completion Time (week) | Crashed Completion time (week) | Crashed Cost per week |
| A | - | 5 | 4 | $500 |
| B | A | 6 | 5 | $400 |
| C | - | 10 | 8 | $500 |
| D | B, C | 9 | 8 | $700 |
| E | D | 5 | 4 | $600 |
| F | E | 7 | 6 | $500 |
| G | D | 10 | 9 | $800 |
- Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. Mark: 4
- Highlight the critical and non-critical activities of the finally completed project by taking into account the crashed times of activities. Mark: 2