Question: Activity Preceding activity Normal Time Crash Time Cost per day to crash A - 8 3 600 B A 7 * 300 C A, B

Activity

Preceding activity

Normal Time

Crash Time

Cost per day to crash

A

-

8

3

600

B

A

7

*

300

C

A, B

6

2

500

D

C

8

*

400

E

B

4

1

350

F

D, E

6

4

100

G

D, F

3

2

550

Projects budget per day $800

a. Draw an AON diagram based on the activities and their relationships given in the table. b. Develop a crashing schedule [ Replace the * with any value in between 3-5]