Question: Activity Preceding activity Normal Time Crash Time Cost per day to crash A - 8 3 600 B A 7 * 300 C A, B
| Activity | Preceding activity | Normal Time | Crash Time | Cost per day to crash |
| A | - | 8 | 3 | 600 |
| B | A | 7 | * | 300 |
| C | A, B | 6 | 2 | 500 |
| D | C | 8 | * | 400 |
| E | B | 4 | 1 | 350 |
| F | D, E | 6 | 4 | 100 |
| G | D, F | 3 | 2 | 550 |
| Projects budget per day $800 |
a. Draw an AON diagram based on the activities and their relationships given in the table. b. Develop a crashing schedule [ Replace the * with any value in between 3-5]