Question: (please answer correctly) Activity Preceding activity Normal Time Crash Time Cost per day to crash A 7 2 500 B A 5 300 A 8

(please answer correctly) (please answer correctly) Activity Preceding
Activity Preceding activity Normal Time Crash Time Cost per day to crash A 7 2 500 B A 5 300 A 8 8 D B, C 6 400 E B, C 3 350 TE D 7 100 G EF 3 550 Project's budget per day $500 a. Draw an AON diagram based on the activities and their relationships given in the table. (2 Marks) b. Develop a crashing schedule [ Replace the * with any value in between 3-5)