Question: Activity Preceding activity Normal Time Crash Time Cost to crash A - 5 3 $200 B - 4 3 $300 C A 6 5 $300
Activity Preceding activity Normal Time Crash Time Cost to crash A - 5 3 $200 B - 4 3 $300 C A 6 5 $300 D B 5 4 $100 E A, C, D 7 6 $100
Projects budget per day $500
a. Draw a AON diagram and determine which activities are on the critical path, its length, and the length of the other path. (2 marks) b. Develop a crashing schedule to show how the activities on the critical and other paths can be crashed. (3 marks) c. After crashing the activities as per the crashing rules what will be the duration of the project? (2 mark)
(Its an emergency, please answer all within 1 hr)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
