Question: Activity Preceding Activity Optimistic Time Probable Time Pessimistic Time A - 2 3 4 B A 3 5 7 C B 1 2 3 D

Activity

Preceding Activity

Optimistic Time

Probable Time

Pessimistic Time

A

-

2

3

4

B

A

3

5

7

C

B

1

2

3

D

C

2

3

10

E

B

5

6

7

F

D

4

8

12

G

B

1

2

3

H

G

3

4

11

I

E,G

4

5

6

J

F,H,I

3

3

3

K

J

3

5

10

a). Tabulate the ES, EF, LS, LF and the slack of each activity. (4 marks)

b). Demonstrate the project activities and their respective expected times in a Gantts Chart. (8 marks)

Pls explain more details how to get it the ES, EF, LS, LF and the slack of each activity. ? Because I Dont know how to get pls help!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!