Question: Activity Preceding Activity Optimistic Time Probable Time Pessimistic Time A - 2 3 4 B A 3 5 7 C B 1 2 3 D
| Activity | Preceding Activity | Optimistic Time | Probable Time | Pessimistic Time |
| A | - | 2 | 3 | 4 |
| B | A | 3 | 5 | 7 |
| C | B | 1 | 2 | 3 |
| D | C | 2 | 3 | 10 |
| E | B | 5 | 6 | 7 |
| F | D | 4 | 8 | 12 |
| G | B | 1 | 2 | 3 |
| H | G | 3 | 4 | 11 |
| I | E,G | 4 | 5 | 6 |
| J | F,H,I | 3 | 3 | 3 |
| K | J | 3 | 5 | 10 |
a). Tabulate the ES, EF, LS, LF and the slack of each activity. (4 marks)
b). Demonstrate the project activities and their respective expected times in a Gantts Chart. (8 marks)
Pls explain more details how to get it the ES, EF, LS, LF and the slack of each activity. ? Because I Dont know how to get pls help!