Question: Using the critical path analysis, answer following questions: (1a) Based on expected tasks' durations, what is the estimated completion time for this project? (1b) What
Using the critical path analysis, answer following questions:
(1a) Based on "expected" tasks' durations, what is the estimated completion time for this project? (1b) What is the likelihood (probability) that the project will be completed in 40 weeks?
| TASK DESCRIPTION AND TIME ESTIMATES (WEEKS) | |||||||
| Task | Description | Predecessor | Most Optimistic | Most Likely | Most Pessimistic | ||
| A | Requirements | - | 2 | 3 | 4 | ||
| B | Market Assesment | A | 4 | 7 | 10 | ||
| C | Design | A | 5 | 6 | 7 | ||
| D | Development | C | 6 | 7 | 14 | ||
| E | Testing | D | 7 | 9 | 11 | ||
| F | Revisions | B,E | 4 | 5 | 6 | ||
| G | Documentation | D | 3 | 6 | 9 | ||
| H | Quality Assurance | C,E | 1 | 4 | 7 | ||
| I | Pricing | B | 2 | 2 | 2 | ||
| J | Production | F,G,H,I | 3 | 6 | 9 | ||
| K | Distribution | J | 2 | 3 | 4 | ||