Question: activity preceding duration (days) A 3 B 7 C A 5 D A, B 3 E C 8 F C, D 9 G E 4

activity

preceding

duration (days)

A

3

B

7

C

A

5

D

A, B

3

E

C

8

F

C, D

9

G

E

4

Draw network diagram node and find critical path (how many days?). Use a dummy if it's necessary.

Please write clearly so that I can understand easily. Thanks in advance!