Question: Activity Preceding Time AON analysis problems Activity Preceding Time A 8 B 3 C A 7 D A,B 3 E C 4 F D 9

Activity Preceding Time

Activity Preceding Time AON analysis problems

AON analysis problems Activity Preceding Time A 8 B 3 C A 7 D A,B 3 E C 4 F D 9 What is project completion time? What is the slack of activity B? What is the slack of activity C? What is the ES of activity D? What is the LF of activity D