Question: Activity Predecessor Duration A (-) 4 B A 10 C A 8 D B,C 16 E B,C 16 F B,C 14 G D,F 2 H
| Activity | Predecessor | Duration |
| A | (-) | 4 |
| B | A | 10 |
| C | A | 8 |
| D | B,C | 16 |
| E | B,C | 16 |
| F | B,C | 14 |
| G | D,F | 2 |
| H | E | 4 |
| I | G | 1 |
| J | I | 6 |
| K | J | 1 |
| L | E | 12 |
| M | E | 12 |
| N | L,M | 1 |
| O | H,K,N | (-) |
What is critical path?
Find ES,EL,LS, LF, and slack time