Question: The network below represents a project being analyzed by the critical path method. Activity durations in weeks, are given in the following table and required

The network below represents a project being analyzed by the critical path method. Activity durations in weeks, are given in the following table and required that a the network diagram be drawn:
Activity Preceding Duration
A -- 9
B A 2
C A 12
D A 5
E B 6
F B 8
G C, F 3
H D 2
I H 8
J G, I 6
K E, J 2
a Draw the network diagram. (10 marks)
b Which activities form the critical path? (6 marks)
c How much slack exists at activities A and F? (4 marks)
d What is the duration of the critical path? (5 marks)
The network below represents a project being analyzed by the critical path method. Activity durations in weeks, are given in the following table and required that a the network diagram be drawn:
Activity Preceding Duration
A -- 9
B A 2
C A 12
D A 5
E B 6
F B 8
G C, F 3
H D 2
I H 8
J G, I 6
K E, J 2
a Draw the network diagram. (10 marks)
b Which activities form the critical path? (6 marks)
c How much slack exists at activities A and F? (4 marks)
d What is the duration of the critical path? (5 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!