Question: Activity Predecessor Duration in Months Start 0 A Start 6 B A, E 2 C B 2 D C 3 E Start 1 F A,

Activity

Predecessor

Duration in Months

Start

0

A

Start

6

B

A, E

2

C

B

2

D

C

3

E

Start

1

F

A, E

1

G

B, F

7

Finish

D, G

0

Draw an AON (Activity on Node) diagram for the above project.

Indicate the ES (Earliest Start), EF (Earliest Finish), LS (Latest Start), LF (Latest Finish) times for each of the activities A through G.

What are the slacks for each of the activities A through G?

What is the critical path(s)?

How many months does it take to complete the project according to the critical path analysis?

If you increase the duration of activity D to 6 months, how does the critical path change?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!