Question: activities in a project, predecessors and duration for each activity. Activity Predecessor Duration in Months Start 0 A Start 6 B A, E 2 C
activities in a project, predecessors and duration for each activity.
| Activity | Predecessor | Duration in Months |
| Start | 0 | |
| A | Start | 6 |
| B | A, E | 2 |
| C | B | 2 |
| D | C | 3 |
| E | Start | 1 |
| F | A, E | 1 |
| G | B, F | 7 |
| Finish | D, G | 0 |
Draw an AON (Activity on Node) diagram for the above project.
Indicate the ES (Earliest Start), EF (Earliest Finish), LS (Latest Start), LF (Latest Finish) times for each of the activities A through G.
What are the slacks for each of the activities A through G?
What is the critical path(s)?
How many months does it take to complete the project according to the critical path analysis?
If you increase the duration of activity D to 6 months, how does the critical path change?
Listed below are the tasks of a project, the precedents and durations in days.
| Task | Predecessors | Duration |
| A | - | 3 weeks |
| B | - | 4 |
| C | A | 2 |
| D | C | 5 |
| E | B | 7 |
| F | D, E | 1 |
| G | D | 4 |
| H | F, G | 5 |
Draw an AOA (Activity on Arrow) diagram of the project.
Indicate the ES (Earliest Start), EF (Earliest Finish), LS (Latest Start), LF (Latest Finish) times for each of the activities A through H.
Tabulate the slacks of the tasks.
What is the critical path(s)
How many weeks does it take to complete the project according to the critical path analysis?
An activity has three estimates: Optimistic = 10 weeks, Pessimistic = 25 weeks, Most-Likely = 15 weeks. What is the estimate according to the three-point estimation method for this activity? What is the standard deviation for this activity?
A project node has ES=21 weeks, LS=37 weeks, LF=39 weeks. Compute the duration, float (slack), and EF for this node.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
