Question: Activity Predecessor Duration ( weeks ) Budget Actual Cost Complete % a 2 3 0 0 4 0 0 1 0 0 b 3 2

Activity Predecessor Duration (weeks) Budget Actual Cost Complete %
a 2300400100
b 3200180100
c a 2250300100
d a 560040020
e b,c 440020020At week 6 the estimated cost of the project at completion (EAC) with no decimal places is calculated as ......
(Assume that the accuracy of the estimates to date has not been good and many of the assumptions made are no longer valid.)