Question: Activity Predecessor Duration ( weeks ) Budget Actual Cost Complete % a 2 3 0 0 4 0 0 1 0 0 b 3 2
Activity Predecessor Duration weeks Budget Actual Cost Complete
a
b
c a
d a
e bc At week the estimated cost of the project at completion EAC with no decimal places is calculated as
Assume that the accuracy of the estimates to date has not been good and many of the assumptions made are no longer valid.