Question: Activity Predecessor Normal Duration Day Normal Cost (RM) Crash Duration days Crash Cost (RM) A - 5 250 3 320 B A 4 300 3

Activity

Predecessor

Normal Duration Day

Normal Cost (RM)

Crash Duration days

Crash Cost (RM)

A

-

5

250

3

320

B

A

4

300

3

400

C

A

6

350

3

800

D

B,C

3

300

2

350

Table 2 Cost Duration

(15 Marks)

b) A communications plan enables you to effectively deliver information to appropriate stakeholders. The plan will identify the messages you need to promote, to whom you're targeting those messages, and on which channels. Tabulate a communication plan for the following information based on your OWN analysis:

  1. Milestone report
  2. Time/cost report
  3. Risk report
  4. Issues
  5. Team meeting

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!