Question: Activity Predecessor Normal Duration Day Normal Cost (RM) Crash Duration days Crash Cost (RM) A - 5 250 3 320 B A 4 300 3
| Activity | Predecessor | Normal Duration Day | Normal Cost (RM) | Crash Duration days | Crash Cost (RM) |
| A | - | 5 | 250 | 3 | 320 |
| B | A | 4 | 300 | 3 | 400 |
| C | A | 6 | 350 | 3 | 800 |
| D | B,C | 3 | 300 | 2 | 350 |
Table 2 Cost Duration
(15 Marks)
b) A communications plan enables you to effectively deliver information to appropriate stakeholders. The plan will identify the messages you need to promote, to whom you're targeting those messages, and on which channels. Tabulate a communication plan for the following information based on your OWN analysis:
- Milestone report
- Time/cost report
- Risk report
- Issues
- Team meeting
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
