Question: Activity Predecessor Normal Duration Normal Cost Crash Time Crash Cost A -- 4 200 3 900 B -- 5 300 4 1200 C F, E

Activity Predecessor Normal Duration Normal Cost Crash Time Crash Cost A -- 4 200 3 900 B -- 5 300 4 1200 C F, E 2 100 1 900 D A 6 400 1 500 E B 1 100 -- -- F D 3 200 1 400 G F 4 200 3 600 H B 5 300 3 400 I H 2 100 1 800 - Draw the AON network diagram - Find the Critical Path - What is the Critical Time - What is the Float of B - What is the normal cost of the project - Crash the project till project duration (CT) reaches 10 days, what is the critical path and the crash costs for the project 

Draw the AON network diagram

Find the Critical Path

What is the Critical Time

What is the Float of B

What is the normal cost of the project

Crash the project till project duration (CT) reaches 10 days, what is the critical path and the crash costs for the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!