Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost / day Max Crash A - 6 $ 5 0 0 4 $

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day Max Crash
A -6 $5004 $1,500 $5002
B -5 $4003 $2,000 $8002
C B 8 $7007 $1,600 $9001
D A, C 3 $2002 $700 $5001
E A, C 4 $300----
F B 9 $8006 $2,900 $7003
G D 6 $5005 $800 $3001
H E, F 7 $6004 $1,800 $4003