Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A - 5 $ 5 0 0 3 $ 1 , 5 0 0 B

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
A -5 $5003 $1,500
B -4 $4002 $2,000
C B 7 $7006 $1,600
D A, C 2 $2001 $500
E A, C 3 $300--
F B 8 $8005 $2,900
G D 5 $5004 $1,000
H E, F 6 $6003 $1,800