Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost per day Max Crash Time A None 5 $ 5 0 3 $
Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost per day Max Crash Time
A None $ $
B None
C b
D ac
E ac NA NA NA
F b
G d
H ef
What is the critical path, time, and cost for an allnormal level of project activity?
Calculate the crash costperday all activities may be partially crashed
See column H in the table above
Find the optimal way of getting an day delivery time.
Crash activities day at a time they can be partially crashed
Project cost Critical activties
Find the optimal way of getting a day delivery time. What is the project cost?
Crash cheapest activities that impact project time using the Gantt chart until you get days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
