Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost per day Max Crash Time A None 5 $ 5 0 3 $

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost per day Max Crash Time
A None 5 $503 $1502
B None 44022002
C b 77061601
D a,c 2201501
E a,c 330 NA NA NA
F b 88052903
G d 55041001
H e,f 66031803
1) What is the critical path, time, and cost for an all-normal level of project activity?
2) Calculate the crash cost-per-day (all activities may be partially crashed).
See column H in the table above
3) Find the optimal way of getting an 18-day delivery time.
Crash activities 1 day at a time (they can be partially crashed).
Project cost Critical activties
4) Find the optimal way of getting a 16-day delivery time. What is the project cost?
(Crash cheapest activities that impact project time using the Gantt chart until you get 16 days)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!