Question: Activity Predecessor Optimistic Most Likely Pessimistic Duration Standard Deviation Duration in Months A 4 7 10 B 7 5.5 7 C 25 33 41 D
Activity Predecessor Optimistic Most Likely Pessimistic Duration Standard Deviation Duration in Months A 4 7 10 B 7 5.5 7 C 25 33 41 D B 20 23 32 E C 1 2 15.5 F D 4 7 22 G A, B 22 10 10 H E 5 9 19 I G 4 3 26 J F, G 12 7 20
Use the information above and draw a network diagram showing the L/S, E/S, E/F, L/F, Slack, and Critical Path