Question: QUESTION THREE [ 2 0 ] The table below provides the duration estimates in days for a construction project. begin { tabular } {
QUESTION THREE
The table below provides the duration estimates in days for a construction project.
begintabularlllll
hline Activity & Predecessor & Optimistic Time & Most Likely Time & begintabularl
Pessimistic
Time
endtabular
hline A & & & &
hline B & & & &
hline C & AB & & &
hline D & C & & &
hline E & C & & &
hline F & E & & &
hline
endtabular
begintabularlllll
hline G & C & & &
hline H & DF & & &
hline I & GF & & &
hline J & HI & & &
hline
endtabular
Determine the expected completion time for each activity.
Complete the table below by filling in the missing values. You are not required to show the network diagram in your answer sheet. Simply write to and insert the missing values on your answer sheet
begintabularlllllll
hline Activity & Duration & ES & LS & EF & LF & SLACK
hline A & & & & & &
hline B & & & & & &
hline C & & & & & &
hline D & & & & & &
hline E & & & & & &
hline F & & & & & &
hline G & & & & & &
hline H & & & & & &
hline I & & & & & &
hline J & & & & & &
hline
endtabular
What do you understand about the term critical path" and determine the critical path and its duration for the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
