Question: Activity Predecessor ( s ) Duration ( in days ) # of cranes needed A - 3 6 B A 2 1 C B 5

Activity Predecessor(s) Duration (in days) # of cranes needed
A -36
B A 21
C B 55
D B 42
E C 94
F C,D 24
G E,F 16
Given the resource constraint (i.e., only 6 cranes are available for the project), discuss the potential over-allocation of this resource and how to resolve it by responding to the following questions:
Identify the days when the resource is over-allocated.
How will you resolve the over-allocation?
What is the new project duration?
What is the new critical path?