Question: QUESTION THREE [20] 3.1 Given the network diagram below, tabulate the precedence table including columns for Activity, predecessor and duration in days (10) 3.2 Complete

 QUESTION THREE [20] 3.1 Given the network diagram below, tabulate the

QUESTION THREE [20] 3.1 Given the network diagram below, tabulate the precedence table including columns for Activity, predecessor and duration in days (10) 3.2 Complete the forward and backward pass, calculate the slack/float and complete the missing numbers in the table below. Insert 3.2.1 to 3.2.8 and insert your answers. (8) 3.3 Identify the critical path for this project and the overall project duration (2)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!