Question: Activity Predecessor Successor Time Cost Time Cost A - - - B , C 5 $ 6 0 2 $ 1 2 5 B A

Activity Predecessor Successor Time Cost Time Cost
A --- B, C 5 $602 $125
B A D, C 470290
C A, B D 6803150
D B, C ---340160
What is the normal project completion time, given the information above?