| Normal | Normal | Crash | Crash | |||
| Activity | Predecessor | Successor | Time | Cost | Time | Cost |
| A | --- | B, C | 5 | $60 | 2 | $150 |
| B | A | D | 4 | 70 | 2 | 90 |
| C | A | D | 6 | 80 | 3 | 155 |
| D | B, C | --- | 3 | 40 | 2 | 60 |
- A.
ABCD.
- B.
ABD.
- C.
ACD.
- D.
AC
- E.
Not enough information is provided.
Given the information in Question 1, What is the normal project completion time,
- A. 11
- B. 12
- C. 13
- D. 14
- E. 18
Reset Selection Given the information in Question 1, what is the project cost if the project is crashed by one day?
- A. $250
- B. $260
- C. $270
- D. $275
- E. None of the above
Reset Selection
Given the information in Question 1, what is the project cost if the project is crashed by two days?
- A. $250
- B. $270
- C. $295
- D. $500
- E. None of the above.