Question: Activity Predecessor Time ( days ) A - - - 2 B - - - 5 C - - - 1 D B 1 0

Activity Predecessor Time (days)
A ---2
B ---5
C ---1
D B 10
E A,D 3
F C 6
G E,F 8
Match the activity with its slack time.
Question 21 options:
2
0
3
11
1
13