Question: Activity Predecessor Time (days) Slack A --- 30 B --- 10 C --- 7 D B 12 E B 5 F C 6 G F

Activity

Predecessor

Time (days)

Slack

A

---

30

B

---

10

C

---

7

D

B

12

E

B

5

F

C

6

G

F

2

H

F

12

I

D

5

J

E,G

6

K

I,J,H

10

L

H

12

M

K

3

  1. How many days will the project take to complete? Take a screenshot showing your project activities and schedule and insert it in the space below. You might want to zoom out your browser window a little to capture everything. (As a hint the answer is 40, but this is not obvious from the table above). Assuming you set the starting date as 3/1 your project should complete on 4/9 remember weekends included)

2. What is the critical path and what are the slack times for each activity? Once you identify the slack times, fill the appropriate column in the table above with the slack time for each activity. FYI - A quick way to determine if an activity is on the critical path is if you drag that activity to the right, TeamGantt will adjust all dependent activities and you will be able to determine if the project completion date will be affected.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!