Question: pts Question 11 Given the project within the table below, calculate the following: Activity Predecessor Time (days) 2.5 A 3.7 B 7.5 C AC 8.8

pts Question 11 Given the project within the
pts Question 11 Given the project within the table below, calculate the following: Activity Predecessor Time (days) 2.5 A 3.7 B 7.5 C AC 8.8 D 10 F BE F 4.2 9.7 G H G 11.5 a. What is the project length? Select b. What activities are on the critical path? [Select) c. How much slack is in activity A? (Select] and activity G? [ Select 1 d. What is the Late Start / Late Finish for activity E? (Select] e. What would happen to the overall project length if activity A was delayed by 6 days, now taking a total of 8.5 days? (Select]