Question: Activity Predecessor Time (wks) Slack D A 3 B 2 C A, B 4 D B 5 C F N W H E G C

Activity Predecessor Time (wks) Slack D A 3 B 2 C A, B 4 D B 5 C F N W H E G C H G 4 - C 7 - L 2 For the project above, please provide the slack time for each activity along with the work justifying your answers