Question: Need the Slack Weeks for c. Consider the following data for a project to reorganize the office space at Platinum Financial Advisors: Activity Expected Time
Need the Slack Weeks for c.
Consider the following data for a project to reorganize the office space at Platinum Financial Advisors:
| Activity | Expected Time (weeks) | Immediate Predecessor(s) |
| A | 3 | |
| B | 2 | |
| C | 3 | A |
| D | 5 | B |
| E | 6 | C, D |
| F | 7 | D |
a. Choose the correct network diagram for this project.
b. Identify the critical path and estimate the project's duration.
The critical path is path B-D-F and the project duration is 14 weeks. (Enter your response as an integer.)
c. Calculate the slack for each activity. (Enter your responses as integers.)
| Activity | |
|
Slack (weeks) | |
| A | enter your response here? |
| B | enter your response here? |
| C | enter your response here? |
| D | enter your response here? |
| E | enter your response here? |
| F | enter your response here? |