Question: Activity | Predecessors Description Duration 1 Start job 1 2 1 Relocate electric 6 3 1 Excavate 5 4 3 Install pipe section #1 10

Activity | Predecessors Description Duration 1Activity | Predecessors Description Duration 1Activity | Predecessors Description Duration 1Activity | Predecessors Description Duration 1Activity | Predecessors Description Duration 1Activity | Predecessors Description Duration 1Activity | Predecessors Description Duration 1

Activity | Predecessors Description Duration 1 Start job 1 2 1 Relocate electric 6 3 1 Excavate 5 4 3 Install pipe section #1 10 5 4 Backfill section #1 5 6 4 Install pipe section #2 12 7 5,6 Backfill section #2 8 8 6 Test pipe sections 3 9 7,8 Grade and sod 7 10 2,8 Install manhole 3 11 10 Test relocated electric 12 9,11 Final inspection 1 N Of the following images which is the correct Activity on Node (AON) rendering of this project? Solve the problem using the Critical Path Method. Enter the earliest start time for each activity in the table below: Activity Earliest Start 1 2 3 4. 5 6 7 8 9 10 11 17 Enter the earliest finish time for each activity in the table below: Activity Earliest Finish 1 1 1 2 3 4 5 6 7 8 9 10 11 12 Enter the latest start time for each activity in the table below: Activity Latest Start 1 2 3 3 4 5 6 CO 7 8 9 10 11 12 Enter the latest finish time for each activity in the table below: Activity Latest Finish 1 2 3 4 5 6 7 8 9 10 11 12 Calculate and enter the slack for each activity in the table below:: Activity Slack 1 2 2. 3 3 4 5 6 7 00 8 9 10 11 12 Select all critical jobs below 1 N 3 4 5 6 7 00 9 10 11 12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!