Question: Activity Predecessors Duration ( weeks ) A - 4 B - 5 C A 2 D B 6 E D 3 F C 6 G

Activity Predecessors Duration
(weeks)
A -4
B -5
C A 2
D B 6
E D 3
F C 6
G E, F 6
Normal Crashed
Activity Cost Duration
(weeks)
Extra Cost Duration
(weeks)
A 5,00044,0003
B 10,00053,0002
C 4,00025,0001
D 4,50063,0004
E 2,000310002
F 7,500650004
G 3,000630004
a) Construct the projects network. (5 points)
b) Identify the critical path and the total duration of the project. (5
points)
c) Identify which activities have slack time. (5 points)
d) After 2 iterations of crashing, what is the total duration of the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer