Question: Activity Predecessors Duration ( weeks ) A - 4 B - 5 C A 2 D B 6 E D 3 F C 6 G
Activity Predecessors Duration
weeks
A
B
C A
D B
E D
F C
G E F
Normal Crashed
Activity Cost Duration
weeks
Extra Cost Duration
weeks
A
B
C
D
E
F
G
a Construct the projects network. points
b Identify the critical path and the total duration of the project.
points
c Identify which activities have slack time. points
d After iterations of crashing, what is the total duration of the
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
