Question: activity predecessors normal_time crash_time normal_cost crash_cost A 5 2 4000 13000 B A 5 3 3000 5000 C B 6 2 2000 12000 D C

activity predecessors normal_time crash_time normal_cost crash_cost A 5 2 4000 13000 B A 5 3 3000 5000 C B 6 2 2000 12000 D C 1 1 3000 3000 E B 4 2 4000 8000 F E 7 3 5500 11500 The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? (Only enter the name of the activity