Question: 1 point activity predecessors normal_time crash_time normal_cost crash_cost 5 3 4000 9000 3500 5500 4 2000 8000 m wn WD 3000 7000 ANA. 4000 14500

 1 point activity predecessors normal_time crash_time normal_cost crash_cost 5 3 4000

1 point activity predecessors normal_time crash_time normal_cost crash_cost 5 3 4000 9000 3500 5500 4 2000 8000 m wn WD 3000 7000 ANA. 4000 14500 6 5500 8500 The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? (Only enter the name of the activity. Lower or uppercase both work. Ex: A or a. Copyrighted content. Cannot be posted. Corsdemir) type your answer... Previous Next