Question: activity predecessors optimistic most likely pessimistic expected time (weeks) variances (weeks^2) A --- 4 7 10 B A 2 8 20 C A 8 12
| activity | predecessors | optimistic | most likely | pessimistic | expected time (weeks) | variances (weeks^2) |
|---|---|---|---|---|---|---|
| A | --- | 4 | 7 | 10 | ||
| B | A | 2 | 8 | 20 | ||
| C | A | 8 | 12 | 16 | ||
| D | B | 1 | 2 | 3 | ||
| E | D,C | 6 | 8 | 22 | ||
| F | C | 2 | 3 | 4 | ||
| G | F | 2 | 2 | 2 | ||
| H | F | 6 | 8 | 10 | ||
| I | E,G,H | 4 | 8 | 12 | ||
| J | I | 1 | 2 | 3 | ||
a. Calculate the expected times and variances in the above table.
b. Draw a network and determine the critical path based on the expected completion times.
WILL GIVE LIKE, THANKS.