Question: activity predecessors optimistic most likely pessimistic expected time (weeks) variances (weeks^2) A --- 4 7 10 B A 2 8 20 C A 8 12

activity predecessors optimistic most likely pessimistic expected time (weeks) variances (weeks^2)

A

---

4

7 10
B A 2 8 20
C A 8 12 16
D B 1 2 3
E D,C 6 8 22
F C 2 3 4
G F 2 2 2
H F 6 8 10
I E,G,H 4 8 12
J I 1 2 3

a. Calculate the expected times and variances in the above table.

b. Draw a network and determine the critical path based on the expected completion times.

WILL GIVE LIKE, THANKS.