Question: Activity Processing Time (Mins) Parallel Processing Stations 1 15 mins 1 N 40 mins 4 3 20 mins 2 4 10 mins 2 5 20

Activity Processing Time (Mins) Parallel
Activity Processing Time (Mins) Parallel Processing Stations 1 15 mins 1 N 40 mins 4 3 20 mins 2 4 10 mins 2 5 20 mins 1 The bottleneck activity for the process shown above is: O Activity 2 O Activity 4 Activity 3 Activity 5