Question: Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000 C 12,000 13,000 11,000 D 8,000 10,000 12,000 E
| Activity | PV (in $) | EV (in $) | AC |
| A | 9,200 | 10,000 | 9,700 |
| B | 23,000 | 20,000 | 18,000 |
| C | 12,000 | 13,000 | 11,000 |
| D | 8,000 | 10,000 | 12,000 |
| E | 10,000 | 12,000 | 13,000 |
| F | 7,000 | 9,000 | 10,000 |
| G | 8,000 | 9,000 | 10,000
|
- A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CPI? What meaning do you derive from the CPI?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
