Question: Activity Start End Duration (days) 0 3 3 3 9 6 8 9 1 1 5 9 4 A B C D E F G

Activity Start End Duration (days) 0 3 3 3 9 6 8Activity Start End Duration (days) 0 3 3 3 9 6 8

Activity Start End Duration (days) 0 3 3 3 9 6 8 9 1 1 5 9 4 A B C D E F G H I 9 14 5 7 9 2 14 21 7 4 7 3 21 23 2 J J 23 32 9 1- Construct the corresponding Gantt chart 2- What is the expected completion time of this project? NB: All the answers should be provided by your hand writing